Appendix A. Case Studies
The purpose of the case study summaries presented in this chapter is to provide an overview of the steps involved with remediating contaminated sediments. Case studies presented in this appendix typically include the following:
- contact information
- brief summary of site characteristics and the remedy employed
- site description including environment, chemicals of concern, primary sources, site history, and a summary of the CSMconceptual site model
- remedial objectives
- remedial approach
- monitoring approach
- references
Table A-1 presents a list of the case study descriptions presented in this appendix, including a summary of the general categories of remedial components (removal, cappingTechnology which covers contaminated sediment with material to isolate the contaminants from the surrounding environment., MNR/EMNR, or a combination of these) included at each site. Table A-2 presents a list of the various chemicals of concern associated with each case study.
Each case study description can be accessed by clicking on the site name in Table A-1 or Table A-2.
|
Case Study Site |
Date |
EPA Region |
Remedy Description |
Removal |
Capping |
MNR or EMNR |
|---|---|---|---|---|---|---|
|
2009 |
3 |
Reactive mat with mixture of peat and compost bioaugmented with dechlorinating microbes |
X |
|||
|
2004 2007 |
3 |
X |
||||
|
1998 |
4 |
Dredging and capping |
X |
X |
|
|
|
10 |
Removal, capA covering over material (contaminated sediment) used to isolate the contaminants from the surrounding environment., MNR |
X |
X |
X |
||
|
|
10 |
Removal, isolation cap, thin cap, MNR |
X |
X |
X |
|
|
2005 |
2 |
Drying pad dewatering; wet cells for decanting; contaminated sediments landfilled |
X |
|
x |
|
|
2009 |
1 |
Removal and cap |
X |
X |
|
|
|
|
10 |
Source control, hotspot removal (dredging), and MNR |
X |
|
X |
|
|
1989
2000 |
10 |
MNR, and dredging and capping |
X |
X |
X |
|
|
2007 |
5 |
Dewatered; drying pads, sand and activated charcoal filtering; landfilled; CAMU; PCB and VOC disposed off site at permitted facility |
X |
|
X |
|
|
2005 |
5 |
GLLA demo; mechanical dredging and disposal |
X |
X |
|
|
|
1992 |
3 |
Dewatered with sand bags & cofferdams; stabilized with fly ash & kiln dust then disposed of in TSCA/RCRA landfills. 230 yd3 incinerated |
X |
|
X |
|
|
1993 |
3 |
Removal |
X |
|
|
|
|
1997 |
10 |
Dewatered; hotspot CDF disposal; large material landfilled; clean sediment backfill, capping |
X |
X |
X |
|
|
1998 |
|
Removal, on-site disposal |
X |
|
|
|
|
1992 |
6 |
Cofferdam dewatering; partially dewatered sediments mixed with cement & barged to offload & disposed at RCRA-compliant landfill |
X |
|
|
|
|
1998 |
5 |
Removal hydraulic cutterhead with swinging ladder |
X |
|
|
|
|
2002 |
5 |
Removal auger, MNR |
X |
|
|
|
|
2009 |
5 |
Removal swinging ladder and capping |
X |
X |
|
|
|
2013 |
5 |
Proposed removal and off-site disposal |
X |
|
|
|
|
2009 |
5 |
MNR 20 miles of river |
|
|
X |
|
|
1999 |
3 |
Removal, GCL cap, GWTS |
X |
X |
|
|
|
1995 |
2 |
Removal and backfilled |
X |
|
|
|
|
2003 |
5 |
Removal disposal |
X |
|
|
|
|
2001 |
2 |
Pilot study of various capping materials, and evaluation of scouring caused by ice jam |
|
X |
|
|
|
1995 |
2 |
Removal, hydraulic dredgingDredging by use of a large suction pipe mounted on a hull and supported and moved about by a boom, a mechanical agitator, or cutter head which churns up earth in front of the pipe, and centrifugal pumps mounted on a dredge which suck up water and loose solids., vacuum dredging and on-site disposal |
X |
|
|
|
|
2005 |
2 |
Hydraulic cutterhead and on-site disposal |
X |
|
|
|
|
2001 |
5 |
Hydraulic dredging, Geotubes for dewatering |
X |
|
|
|
|
2006 |
2 |
Removal, cap, MNR |
X |
X |
X |
|
|
1990 |
2 |
Dredging, cap, and MNR |
X |
X |
X |
|
|
2002 |
1 |
Isolation cap installed on area not dredged; dredged areas backfilled and seeded/replanted. |
X |
X |
|
|
|
2009 |
2 |
Organoclay/sand marine mattress and organoclay RCM |
X |
X |
X |
|
|
2009 |
1 |
Excavation and off-site disposal |
X |
X |
|
|
|
2001 |
10 |
Removal, cap, MNR |
X |
X |
X |
|
|
2007 |
5 |
Creek dewatered and sediment removed; treated with AC prior to disposal |
X |
|
|
|
|
1998 |
4 |
Removal, cap, MNR |
X |
X |
X |
|
|
2005 |
3 |
Source control, excavation and capping |
X |
|
|
|
|
1999 |
6 |
Hydraulic cutterhead dredge |
X |
|
X |
|
|
2001 |
6 |
Removal, MNR |
X |
|
X |
|
|
1987 |
2 |
Excavation |
X |
|
|
|
|
1986 |
2 |
Removal |
X |
|
|
|
|
1993 |
5 |
Hydraulic dredging, cap, MNR |
X |
X |
X |
|
|
2001 |
1 |
Removal |
X |
|
|
|
|
McCormick & Baxter Site, Willamette River (SH6), Portland, OR |
1996 |
10 |
Cap |
X |
X |
|
|
1999 |
9 |
Cap |
|
X |
|
|
|
1997 |
3 |
Mechanical dredging, cap |
X |
X |
|
|
|
2004 |
8 |
Removal, MNR |
X |
|
X |
|
|
2009 |
3 |
Removal, thermal treatment of removed sediments |
X |
|
X |
|
|
1997 |
4 |
Removal and stabilization |
X |
|
|
|
|
1995 |
1 |
Hydraulic cutterhead dredge, slurry pipe to off-site TSCA disposal |
X |
|
|
|
|
2004 |
1 |
Two hydraulic cutterheads, sediments dewatered and disposed in TSCA facility |
X |
|
|
|
|
1996 |
1 |
Removal, removed rock decontaminated |
X |
X |
|
|
|
1998 |
|
Hydraulic dredging; GLLA AOC demo, including AquaBlok |
X |
|
|
|
|
|
5 |
Hydraulic dredging and off-site disposal |
X |
|
|
|
|
2010 |
1 |
Removal hydraulic cutterhead and slurry pumped into Geotextile bags |
X |
|
|
|
|
2010 |
1 |
Cap designed to trap NAPL |
|
X |
|
|
|
1994 |
2 |
Removal and disposal |
X |
|
|
|
|
1998 |
1 |
|
X |
|
||
|
1997 |
5 |
Hydraulic cutterhead dredging and disposal in landfill or hazardous waste landfill depending on concentrations |
X |
|
|
|
|
2009 |
10 |
Bulk organoclay |
|
X |
|
|
|
2005 |
10 |
Debris removal, excavation, and capping |
X |
X |
|
|
|
1996 |
NA |
Removal, stabilized prior to disposal |
X |
|
|
|
|
2010 |
NA |
Dredging and on-site disposal |
X |
|
|
|
|
1996 |
2 |
Mechanical dredging stabilized or shipped to hazardous waste landfill. Concentration dependent |
X |
X |
|
|
|
1986 |
4 |
removal, wetland |
X |
|
|
|
|
2000 |
5 |
Removal, MNR |
X |
|
X |
|
|
2001 |
5 |
Removal, MNR |
X |
|
X |
|
|
2004 |
5 |
Dredging, AC RCM |
X |
X |
|
|
|
1993 |
5 |
Removal |
X |
|
|
|
|
2001 |
1 |
Backhoes and long reach excavators, stabilized w/ lime kiln dust |
X |
X |
|
|
|
1994 |
5 |
Capping, MNR |
|
X |
X |
|
|
2000 |
4 |
Removal, DNAPL recovery |
X |
|
|
|
|
2003 |
5 |
Removal, stabilization of sediment before disposal |
X |
|
|
|
|
1998 |
4 |
Removal, NAPL site capped with AquaBlok |
X |
X |
|
|
|
2000 |
4 |
Cable arm clamshell |
X |
|
|
|
|
1994 |
4 |
MNR |
|
|
X |
|
|
2007 |
5 |
Proposed removal, cap |
X |
X |
|
|
|
1989 |
2 |
Excavation, MNR |
X |
|
X |
|
|
1989 |
5 |
Removal, thermal desorption of removed sediments |
X |
|
|
|
|
West Branch Grand Calumet River (WBGCR) (Reaches 3, 4-5), Hammond, IN |
2010, 2011 |
5 |
AC RCM |
X |
X |
|
|
2003 |
5 |
Removal and disposal, dried and off-site disposal |
X |
|
|
|
|
1992 |
10 |
|
X |
X |
||
|
2005 |
10 |
Dredging, cap, and MNR |
X |
X |
X |
|
|
Contaminants of Concern (compounds other than those listed were not considered) |
||||
|---|---|---|---|---|---|
|
Case Study Site |
PCB |
PAHs |
Metals |
Dioxin |
Other Pollutants |
|
|
|
|
|
Chlorinated aliphatics |
|
|
|
X |
X |
|
|
|
|
|
X |
As, Pb, Cr, Cu |
X |
PCP |
|
|
|
4-MP and phenol |
Hg |
|
|
|
|
X |
|
Hg |
|
|
|
|
X |
|
Hg, Ag, Cu |
|
|
|
|
X |
|
As, Cd, Cu, Pb, Zn |
|
|
|
|
X |
X |
Pb |
|
Pesticides |
|
|
X |
X |
As, Cd, Cu, Hg, Pb, Zn |
|
VOCs and phthalates |
|
|
|
|
|
|
|
|
|
X |
|
Hg, Pb, Zn |
|
Oil and grease |
|
|
X |
|
Hg |
|
VOCs |
|
|
|
|
Cd, Pb, and Zn (variable depending on OU - see case study) |
|
|
|
|
|
X |
Hg, Pb, Cu, Zn |
|
Creosote, PCP |
|
|
|
|
Pb |
X |
|
|
|
|
|
|
|
Ethylene dichloride |
|
|
X |
|
Hg |
|
|
|
|
X |
|
Hg |
|
|
|
|
X |
X |
Hg, Pb, As |
X |
Furan, DDT |
|
|
X |
|
Hg, Pb, As |
X |
Furan, DDT |
|
|
X |
X |
Hg, Pb, As |
X |
Furan, DDT |
|
|
|
|
|
|
DNAPL, VOCs |
|
|
X |
|
|
|
|
|
|
X |
X |
X |
|
Cyanide |
|
|
X |
|
X |
|
|
|
|
X |
|
|
|
|
|
|
X |
|
|
|
|
|
|
|
|
Hg, Cu, Pb, Zn |
|
Methyl mercury |
|
|
|
|
Cr |
|
|
|
|
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
X |
|
|
Coal tar NAPL |
|
|
X |
|
|
|
|
|
|
X |
|
Pb, As |
|
NH4, H2S, petroleum |
|
|
X |
X |
Pb, As, Be |
|
VOCs |
|
|
|
X |
As, Pb, Cr, Cu |
X |
|
|
|
|
X |
|
|
NAPL |
|
|
|
X |
Hg |
|
|
|
|
|
X |
Hg |
|
Methylmercury |
|
|
|
X |
X |
X |
VOCs and pesticides |
|
|
|
|
Cd, Ni, Co |
TCE |
||
|
X |
|
|
|
||
|
|
|
|
|
|
|
|
McCormick & Baxter Site, Willamette River(SH6), Portland, OR 1996 |
|
|
X |
X |
|
|
|
X |
|
X |
|
|
|
X |
X |
|
X |
|
|
|
|
|
As, Cu, Cd, Pb, Zn |
X |
Creosote NAPL |
|
|
|
X |
As, Cr, Cu, Pb, Zn |
|
||
|
X |
|
|
|
||
|
X |
|
X |
|
||
|
X |
|
X |
|
||
|
|
X |
|
NAPL |
||
|
|
|
|
|
||
|
X |
X |
|
|
||
|
X |
X |
|
|
||
|
|
X |
|
VOCs, BTEX, coal tar |
||
|
|
X |
|
coal tar NAPL |
||
|
|
|
|
DNAPL VOCs and SVOCs |
||
|
|
X |
X |
NAPL, VOCs |
||
|
|
X |
|
|
||
|
|
|
Pb |
X |
|
|
|
X |
X |
Cu, Hg, Zn |
Phenanthrene, dibenz(a,h)anthracene, hexachlorobutadine (HCBD) |
||
|
X |
|
|
|
||
|
|
X |
X |
|
||
|
X |
X |
|
Dibenzofurans |
||
|
|
|
Pb |
|
||
|
X |
|||||
|
X |
|||||
|
|
|||||
|
|
|
Mg, Cr, Pb |
Oil and grease |
||
|
X |
X |
|
|
||
|
X |
X |
X |
Coal tar, nitrate, ammonia, waste from explosive manufacturing |
||
|
X |
|
|
|
||
|
X |
|
|
VOCs, SVOCs |
||
|
|
X |
|
|
||
|
|
|
|
Toxaphene |
||
|
X |
|||||
|
X |
|
X |
PPB, DDT, pesticides, brominated compounds, rare earth metals and radioactive contaminants |
||
|
|
|
As |
|
||
|
X |
|
|
|
||
|
West Branch Grand Calumet River (WBGCR) (Reaches 3, 4-5), Hammond, IN 2010, 2001 |
X |
X |
X |
Pesticides |
|
|
|
|
Cr, As, Hg |
Tannery waste |
||
|
|
X |
X |
Creosote and pentachlorophenol |
||
|
X |
X |
X |
TBT |
||
Publication Date: August 2014